Prop C Construction Start Date : June 2008
Prop C Estimated Completion Date: May 2009
Pomerado Rendering
Pomerado Elementary School was built in 1960.
The Principal: Lisa Danzer
Projects planned at Pomerado include:
  • Utility upgrade/efficiency improvements
  • Renovate/upgrade restrooms as needed
  • Modify/expand/renovate library
  • Modernize classrooms, such as lighting, power/data, flooring, and marker boards
  • Renovate/expand staff work area
  • Add/renovate computer laboratory
  • ADA upgrades/compliance
  • Food service area expansion/renovation, including new covered lunch area
  • Site/playground improvements for code and safety compliance
  • Add/upgrade furniture and instructional equipment
  • Upgrade/replace communications and fire alarm systems
hardhat
Accomplished in July
  • Poured concrete footings and concrete walls.
  • Cure the concrete.
  • Backfill and waterproof the back wall.
Planned for August
  • Pour the concrete walkway/ramp.
  • Install all the railings.
  • Complete the conduits and install new lightpoles.
  • Clean up, punchlist and demobilization.
Please keep checking this website periodically for the latest news on our construction progress.
  • ADA Ramp Construction
  • ADA Ramp Construction
  • ADA Ramp Construction
  • ADA Ramp Construction
  • ADA Ramp Construction
  • ADA Ramp Construction
  • ADA Ramp Construction
  • ADA Ramp Construction
  • ADA Ramp Construction
  • ADA Ramp Construction
  • Existing Ramp Removed
Thumbnail panels:
Now Loading